Apollo Beach
Explore a massive 600,000-pound ship loader in just three months, captured in a breathtaking time-lapse condensed to just 60 seconds.
Apollo Beach
Emergency 600,000 Pound Ship Repair and Relocation
An emergency call was placed due to a mechanical issue with the ship loader. The boom cable snapped, causing the boom’s weight to slide backward, hitting the main unit, tearing the rails out of the ground, and derailing the loader. The Gulf Coast Industrial team was assigned to fix the loader, the boom cables, and the rail tracks and relocate the unit.
Job Stats
9000 work hours completed incident- and injury-free
Jacked the ship loader, installed temporary rails
Put derailed 600,000 pounds ship loader back on the track
Repair metal support structure, loader support systems and replace boom cabling
Lifted equipment to make repairs and replace structural steel
Removed temporary systems to achieve full operational status